Monday, October 31, 2011

Project Complete

On Friday, October 28, 2011, after 47 days and an intense schedule, the contractor has completed the final phase of the asphalt overlay project on 41st Street between Minnesota Avenue and Western Avenue. This section of 41st Street is used by 23,000 vehicles per day. This coordinated effort between Asphalt Surfacing Company of Sioux Falls, the local businesses, and the City of Sioux Falls was completed on time and under budget on one of the City’s busiest streets. The City would like to thank the public for their patience during the construction period for this project and other projects along 41st Street. Enjoy the new driving surface!